Headquartered in Carmel, IN, Zotec Partners aims to simplify the healthcare financial experience. Technology is an essential part of the healthcare system. Zotec understands that as fast as technology changes, it is important to design a facility that meets their growing needs while providing successful client outcomes.
CE Solutions was commissioned to design the structural systems for this five-story office building and 463-space parking garage. One of the challenges in the design was at the main entrance. The second-floor cantilever beams spanning 15’ support the three stories above. CE Solutions used large post-tensioned, reinforced concrete transfer girders that were 42” deep.
Size | 124,000 square feet; 463 space parking garage
Constructed | 2021